Residents demand pay for destroyed houses, crops

The road project manager, Mr Wang Sen (left), and Dr Kasirivu Atwooki, the State Minister for Economic Monitoring (2nd left), with other officials inspect an affected water source at the weekend. PHOTO BY ALEX TUMUHIMBISE

Kakumiro. Residents of Kisojo Village in Kyabasaija Sub-county, Kakumiro District are demanding compensation from a Chinese company for destroying their houses and crops during stone blasting.
China Communication Construction Company (CCCC) was contracted to construct the 104-kilometre Mubende-Kakumiro-Kagadi road.
During a meeting with the Minister of State for Economic Monitoring in the Office of the President, Dr Kasirivu Atwooki, at the weekend, the project affected persons, said their open water sources have also been contaminated.

‘‘All houses have developed cracks because of the stone blasting and we were never compensated. The Chinese also promised us two boreholes but we have not received any positive response. Our open surface water sources were contaminated by dust and rock particles from the exercise,’’ Mr Jackson Murokozi, the leader of the affected residents, said.
Mr Cornelius Sebintu, who spoke on behalf of project-affected persons, said the contractor assessed residents staying within a radius of 500 metres from the blasting for compensation before starting the exercise, but they have not yet been paid.

He also said the company violated the terms of engagement with them.
‘‘We agreed with them that they should not work for the whole night and not blast stones before informing us, but they never respected the agreement. We have heard that they want to go and we fear that they might go without compensating us,” Mr Sebintu said. Dr Kasirivu demanded a list of those affected before taking action.
“I want you to compile a full list of all affected persons so that we can help you, especially those whose houses were damaged. I want the report before Tuesday next week,” the minister, also the Bugangaizi West MP, said.

Response
However Mr Wang Xie Fue, the project manager, said they provided provisional piped water to the residents. He also inspected the affected houses with Mr Kasirivu. CCCC also says it has paid out Shs300m in compensation to about 50 claimants, however, compensation claims for houses damaged by its stone-blasting activity are yet to be verified and addressed.
CCCC, citing findings by experts it contracted, also says it has failed to drill boreholes it promised to residents because the area has an extremely low water table. They, however, have one functional borehole on site, which pumps water to a standpipe that serves the community.

UNRA warning
In a recent meeting with affected residents, Ms Allen Kagina, the Uganda National Roads Authority executive director, warned the contractor against acts which infringe on people’s rights.
‘‘It is not right to mistreat our people. Access to water is a human right and covering peoples’ wells is not good,’’ Ms Kagina said.
She attributed some of the challenges to lack of community sensitisation.

The project, which had been set for completion by February, has been pushed to next year because of lack of compensation funds.
The completion rate stands at 55 per cent with already 45 kilometres tarmacked.

NOTE:This story was edited on May 15, 2019 to remove errors.
[email protected]