Masaka vendors reject stalls at new market

Inspection. A section of vendors with a team from Ministry of Local Government inspect stalls at the new market last week. PHOTO BY WILSON KUTAMBA

What you need to know:

Claim. Vendors say the stalls are too small to accommodate their merchandise.

A section of vendors at Masaka Central Market have protested the structural designs of stalls at the new market.
The vendors claim the stalls are too small to accommodate their merchandise.
A joint venture of Multiplex Ltd and Alshams Construction Company Ltd was contracted to do the work at Shs18.45 billion, with sponsorship from the African Development Bank and government of Uganda.
So far, the contractor has completed more than 100 stalls on the first floor of the three-storeyed market building.
Ms Betty Nakayiza, the chairperson of Masaka Central Market Vendors Association, asked the contractor to make adjustments and ensure that all stalls suit the interests of different categories of vendors.

Adjustments
“We are the actual beneficiaries of this market project and we request for reasonable adjustments in the stalls to suit our interests as vendors. At least from 5 ft by 5 ft to 7 ft by 7 ft, every stall,” she said during an inspection exercise of the project last week.
Ms Nakayiza said the stalls lack ample space and walkways for customers.
The most dissatisfied vendors are those dealing in foodstuffs.
Vendors also allege that some stalls have been taken up by politicians.
“We have been hearing this in other areas but we are now experiencing the same. We are determined to fight all those bent on allocating our lock-ups and stalls to outsiders,” Mr Samuel Kato, a vendor, said
Mr Herbert Muhoozi, the market project architect and supervisor, said they have taken note of the vendors’ concerns and the stalls will soon be modified.
“....but this will cost us both time and resources,” he said.
Work on the market, which started in February 2018, is expected to be completed by July 30.
The contractor has so far done 74 per cent of work instead of the projected 94 per cent .
Mr Emmanuel Mwebaze, the contract’s manager in Ministry of Local Government, said compared to the previous months, the contractor has picked up pace.
“We had thought about terminating the contract but we have given the contractor more four months after proving that he can complete the work,” he said.
He appealed to vendors and all Masaka Municipal leaders to support the contractor.
Background

The old Masaka Central Market structure, which was constructed in 1936, was pulled down in 2018 to pave way for the new market. It used to house more than 1,000 vendors.
Current location. Currently, the vendors are operating in makeshift stalls adjacent to Masaka Secondary School main gate.
They have repeatedly urged the contractor to speed up work on the project, saying the open space where they were temporarily relocated is in a poor condition and their merchandise always gets soaked in dirty water whenever it rains.
Facilities. The new market is expected to accommodate more than 2,000 vendors. It will also have an agro-processing facility, stalls, shops, cold rooms, restaurants, a parking yard and loading and offloading areas, drainage ways, solid waste bays, firefighting facilities, among others.